Project Category: Infrastructure
As the result of a weather event in September 2016 several of the water course assets owned by the Clare and Gilbert Valley Council were damaged and required restoration and / or complete replacement. Neo were awarded the contract to bring back into service 114 sites spread within the council boundaries. Each site was assessed by Neo with the client and the superintendent to document the scope of work required.
Neo’s in-house knowledge, experience and resourcing facilitated quality outcomes acknowledge by the many community members and stakeholders within the region. Neo utilised their own concrete division and asphalt arm to provide a one stop shop for the works enabling continuity and flexibility in the delivery.
SCOPE OF WORKS:
• 52 Concrete floodways replaced
• Pavement reinstatement
• Stormwater culverts and pipes
• Concrete wing walls and headwalls cast insitu
• Concrete drainage channels
• Stone pitching
• Asphalt sealing
CONTRACT DETAILS:
• Duration: November 2017—August 2018
• Value: $2.4m
• Client: Clare and Gilbert Valley Council