Third Avenue Everard Park Development
THIRD AVENUE EVERARD PARK DEVELOPMENT
Project Category: Land Development
Neo were successful in negotiating the contract to undertake the civil works on this much publicised new development on the western outskirts of the city. Working directly for the Arcadian Property Group, Neo delivered 20 serviced community title allotments and 7 Torrens Title allotments. The development attracted much public interest and Neo delivered the works whilst working closely with the many and varied stakeholders ensuring all agreed conditions were met and the project delivery met the objectives set out prior to commencement.
SCOPE OF WORKS:
• 4000m3 of imported fill
• Sewer installation
• Potable Water installation
• Electrical and NBN infrastructure
• Pavement construction
• Construction of 2 no. rain gardens
• Reconstruction of existing property frontages
• Stormwater network
CONTRACT DETAILS:
• Duration: April— June2019
• Value: $700,000
• Client: Arcadian Property Group
• Superintendent: WGA